A construction notice shall be filed no less than 90 days before planned commencement of construction. A construction notice for which the applicant requests expedited processing shall be filed not less than 21 days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the 90 or 21 day requirement per OAC 4906-6-03.
Certain types of major utility facilities are subject to accelerated OPSB review. Based on qualifying characteristics, these facility types may be filed with the OPSB as a construction notice application (case code BNR). For additional information, please review the Board's accelerated application process.
OPSB application requirement matrices
There are 3 matrices that provide developers a list to use depending on what type of application they should submit to the Board.