A letter of notification application shall be filed no less than 90 days before the planned commencement of construction. A letter of notification for which the applicant requests expedited processing shall be filed not less than 28 days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the 90 or 28 day requirement per OAC 4906-6-03.
Certain types of major utility facilities are subject to accelerated OPSB review. Based on qualifying characteristics, these facility types may be filed with the OPSB as a letter of notification application (case code BLN). For additional information, please review the Board's accelerated application process.
OPSB application requirement matrices
There are 3 matrices that provide developers a list to use depending on what type of application they should submit to the Board.