19-1066-EL-BTX:Republic Wind Transmission Line

Case Number 19-1066-EL-BTX

Do you want to search other cases?

We have a list with all cases in our catalog

On February 5, 2020, Republic Wind filed a motion in the case record to suspend the procedural schedule. Republic Wind stated that it intends modify the proposed transmission line route. As currently proposed, the Applicant proposes to construct a 7.2-mile long 138 kilovolt (kV) transmission line and a point of interconnection substation in Pleasant and Adams townships adjacent to the existing Fremont Center-Tiffin Center 138 kV transmission line. The project would connect the proposed Republic Wind Farm to the electric grid.

Staff Report of Investigation (includes maps)